Railings and overhead structure have begun to take shape in Aquaman: Power Wave’s station.
The ride’s station now sits on the opposite side of the original design due to the addition of a turntable.
Additional overhead structure has been installed in other areas of the queue.
Aquaman: Power Wave’s retention pond is in the process of being painted a light blue.
A large retaining wall has been constructed to help manage the attraction’s splashdown.
An overall look at construction progress from the back side of the attraction.
Aquaman: Power Wave’s first of two ride vehicles has made its way onto the track.