Lone Star Theatre Demolition, El Diablo (Update 7) & More
Demolition of the Lone Star Theatre performance venue took place this past week. Crews continue to work on El Diablo’s queue area with shade structure installation and other themed lighting and elements.
El Diablo (Update 6), Gold River Adventure (Update 2) & Aquaman Splashdown (Update 3)
Work on El Diablo’s queue line is in full swing as footers have been poured and polls for a future shade structure are going into place. More signage and theming has also been removed from Gold River Adventure.
Aquaman Splashdown (Update 2) & El Diablo (Update 5)
The removal of Aquaman Splashdown pieces continues as ground work around El Diablo begins to clear for the upcoming installation of the queue line.
El Diablo (Update 4), Aquaman Splashdown (Update 1) & Gold River Adventure (Update 1)
El Diablo has gone vertical and main components of the ride are now constructed. We also check out Aquaman Splashdown as pieces are being removed from the attraction.
El Diablo (Update 3) & Chop Six
Footers have been poured for El Diablo while Chop Six has been repainted and new kitchen equipment has arrived to the park.
El Diablo (Update 2)
A closer look at construction progress on El Diablo, including the reopening of the park’s Spain section for Spring Break.